95 questions in this part of the Health and Safety Test (CSCS) bank. Every answer below is the one the bank holds, and the document under each question is where it was written from. They are written from those documents; they are not the questions of the real test, which are not published.
Practise the whole bank in the browserThe same bank as an Android app, on Google Play
All 95 questions
- 1. Working environmentcscs-1
It is your first day on a new site. What must you be given before you start work?
- AA site inductionAnswer
- BA copy of the client contract
- CA written test on site rules
- DA tour of the client's offices
The induction is how you learn the risks of this site and how they are controlled. Every worker gets one, and it is about this site, not about building work in general. If nobody gives you one, ask before you start.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/site-rules-induction.htm
- 2. Working environmentcscs-10
What does a site have to do about drinking water?
- ASell it from a machine in the canteen
- BAlways have it available and clearly markedAnswer
- CProvide it only in hot weather
- DLeave workers to bring their own
Drinking water has to be there all the time, easy to get to and clearly labelled so nobody drinks from the wrong tap. Mains supply is best. If it is stored or bottled it must not be allowed to go stale or get dirty.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/changing-rooms-and-lockers.htm
- 3. Working environmentcscs-11
The Construction (Design and Management) Regulations 2015 deal with drinking water on site. What else do they say about the supply?
- AIt must be tested by a laboratory each month
- BIt must be marked by a sign where neededAnswer
- CIt must be free of charge to visitors only
- DIt must be kept in the site office
Where it is needed for health or safety, the supply has to carry a sign so it cannot be mixed up with water that is not fit to drink. On a site there are often several taps and only some are safe. The sign is what tells you which.
Sourcehttps://www.legislation.gov.uk/uksi/2015/51/schedule/2
- 4. Working environmentcscs-12
You walk past a coil of cable lying across a busy corridor. What is expected of you?
- ASort it out, or tell someone who canAnswer
- BStep over it and carry on
- CWait for the weekly safety walk
- DPut a cone next to it and leave it
Slips and trips are everyone's job, not just the manager's. Either clear the hazard yourself or pass it to a person who can. Leaving it for later is how the next person gets hurt.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/falls.htm
- 5. Working environmentcscs-13
How serious are trips and slips on building sites?
- AThey almost never cause lasting harm
- BAround 1000 a year break bones or dislocate jointsAnswer
- CThey are only a problem on wet days
- DThey mainly affect visitors, not workers
Several thousand construction workers are hurt this way each year, and about a thousand of them break a bone or put a joint out. Most of it comes from untidy walkways and access routes. That makes housekeeping a safety control, not a tidiness habit.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/falls.htm
- 6. Working environmentcscs-14
You need mains powered tools in a long corridor. What is the best way to deal with the leads?
- ATape them to the floor along the wall
- BRun them at high levelAnswer
- CLay them under a sheet of plywood
- DLeave them loose but tell people
A lead off the floor cannot be tripped over. Cordless tools are better still, because then there is no lead at all. Covering a cable helps a little but the hump is still there to catch a foot.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/falls.htm
- 7. Working environmentcscs-149
A firm offers to take your site waste away for cash and no paperwork. What does the law require you to do?
- AGive the waste only to a business authorised to take itAnswer
- BGive it to whoever charges least
- CSplit the load so no one carries too much
- DKeep a photograph of the load instead of paperwork
Waste stays your responsibility after it leaves the gate. The duty of care says you must keep it safe and hand it only to someone authorised to take it. Cheap with no paperwork usually means the load is going somewhere it should not, and the fine comes back to the site.
Sourcehttps://www.gov.uk/government/publications/waste-duty-of-care-code-of-practice
- 8. Working environmentcscs-15
Deliveries keep getting stacked along the footpath through the site. What is wrong with that?
- ANothing, if the stacks are neat
- BIt looks untidy to visiting clients
- CStorage must not block access or escape routesAnswer
- DThe materials may get wet in the rain
A blocked walkway pushes people into traffic routes or onto rough ground, and a blocked escape route is far worse in a fire. Storage areas are meant to be marked out and kept to. Planning deliveries also keeps the pile on site smaller.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/storage.htm
- 9. Working environmentcscs-150
Your firm wants to take its own waste to the tip regularly. What does it need first?
- ATo register as a waste carrierAnswer
- BNothing, own waste is exempt
- CA letter from the client
- DA skip licence from the fire service
Moving your own waste on a regular basis still counts as carrying waste, so the firm has to be registered for it. A one-off is different from regular, and if you are doing it every week it is regular.
- 10. Working environmentcscs-151
What is a waste transfer note for?
- ATo record what waste was handed over, and to whomAnswer
- BTo claim the cost back from the client
- CTo prove the skip was full
- DTo book a slot at the landfill site
It is the paper trail. You fill it in, sign it and keep it, so there is a record of what left the site and who took it. Without it you cannot show that you passed the waste to someone allowed to have it.
Sourcehttps://www.gov.uk/government/publications/duty-of-care-waste-transfer-note-template
- 11. Working environmentcscs-152
Old paint tins, solvent and fluorescent tubes are cleared from a unit. What do you have with this waste?
- AA duty of care over how it is handledAnswer
- BNo duty once it is in the skip
- CA duty only if it leaks
- DA duty only if the client asks
Hazardous waste carries the same duty of care as any other waste, and it is watched more closely because of what it can do. Putting it in the general skip is not disposal, it is passing the problem on.
- 12. Working environmentcscs-153
Someone has tipped a lorry load of rubbish on the edge of the site overnight. Who do you report it to?
- AThe Environment Agency incident hotlineAnswer
- BThe police non-emergency line only
- CNobody, it is on private land
- DThe skip company
Large scale dumping is a waste crime and there is a hotline for it that runs all day and night. Do not move it or sort through it: it may be hazardous, and it is evidence.
- 13. Working environmentcscs-155
Neighbours complain about a strong smell coming from the site. Who deals with that complaint?
- AThe local councilAnswer
- BThe Environment Agency only
- CThe site foreman, informally
- DNobody, smell is not regulated
A smell from a business or a neighbour goes to the council. Waste facilities and industrial premises are handled differently, but for an ordinary site the council is the right door.
- 14. Working environmentcscs-16
Packaging and timber offcuts are building up in the work area. Why should they be cleared often?
- ATo cut down the fire riskAnswer
- BTo keep the skip charges lower
- CTo stop the wood being stolen
- DBecause waste attracts rainwater
Loose combustible waste is fuel waiting for a spark, and a site has plenty of sparks. Clearing it regularly is one of the cheapest fire controls there is. It also keeps the walkways clear at the same time.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/storage.htm
- 15. Working environmentcscs-163
Besides registering as a carrier, what else may a firm need in order to handle waste?
- AA waste permitAnswer
- BA driving permit for the yard
- CA noise licence
- DA works notice from the council
Registration covers carrying it. Depending on what is being done with the waste, a permit may be needed as well. The two are separate, and one does not stand in for the other.
- 16. Working environmentcscs-17
What must be true of the lighting on escape routes while people are working on site?
- AIt can be switched off to save power
- BThey must be kept well litAnswer
- CTorches at the exit doors are enough
- DOnly the exit sign needs to be lit
You cannot escape down a route you cannot see. The route stays lit for as long as anyone is on site, and where daylight does not reach it, lighting that comes on if the main supply fails is needed. It only has to be enough to get out by.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/site-lighting.htm
- 17. Working environmentcscs-176
When does a business have to classify the waste it produces?
- AOnly if the waste turns out to be hazardous
- BAt the end of the job, along with the final account
- COnly when the council asks for the figures
- DBefore it is collected, disposed of or recoveredAnswer
Classifying first is what tells everyone downstream how to handle the load and who is allowed to take it. It also fixes what goes on the paperwork. Working it out at the tip is too late for the people who loaded and carried it.
Sourcehttps://www.gov.uk/how-to-classify-different-types-of-waste
- 18. Working environmentcscs-177
What has to appear in the description of a load of waste leaving site?
- AThe name of the site manager
- BThe waste classification codeAnswer
- CThe value of the load
- DThe weight of the empty vehicle
The description also says whether the load is hazardous, what kind of premises produced it, the substances in it and the process that made it. Anything unusual about it has to be written down as well.
Sourcehttps://www.gov.uk/how-to-classify-different-types-of-waste
- 19. Working environmentcscs-178
A skip already holds hazardous waste and someone wants to tip general rubbish in on top. What does the law say?
- AMixing is allowed if the skip is labelled
- BMixing is allowed if the load is small
- CMixing is allowed if the driver agrees
- DMixing them is illegalAnswer
The rule also stops one hazardous waste being mixed with another. Mixing turns a manageable load into one nobody can classify, and the whole skip then has to be handled as the worse of the two. Keep the streams apart from the start.
Sourcehttps://www.gov.uk/how-to-classify-different-types-of-waste
- 20. Working environmentcscs-179
A firm carries waste for other people without registering. What does it face?
- AA written warning only
- BA fee of fifty pounds
- CAn unlimited fineAnswer
- DA ban on site work for a month
Registering is done with the Environment Agency, and it is what puts the firm on the public register everyone else checks before handing over a load. Transporting, buying, selling, disposing of and arranging waste all need it.
Sourcehttps://www.gov.uk/waste-carrier-or-broker-registration
- 21. Working environmentcscs-18
Someone fits orange lamps in a corridor that has fire signs on the wall. What is the concern?
- AOrange light uses more electricity
- BThe lamps may run too hot to touch
- CThe light may change how safety signs lookAnswer
- DColoured lamps are banned on site
Signs and extinguishers are recognised by their colour. Lighting that shifts that colour can make a sign meaningless at the moment it is needed. Shadows are the other trap, so extra lamps are often needed at stairwells and at the cutting edge of a tool.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/site-lighting.htm
- 22. Working environmentcscs-180
How often does an upper tier waste carrier registration have to be renewed?
- AEvery 3 yearsAnswer
- BEvery year
- CEvery 6 months
- DNever, it lasts for life
A lower tier registration does not need renewing at all. Which tier a firm gets is settled when it registers, and the letter says which one it is. The registration number on that letter starts with the letters CB.
Sourcehttps://www.gov.uk/waste-carrier-or-broker-registration
- 23. Working environmentcscs-181
The management of a registered waste carrier changes. How long is there to tell the Environment Agency?
- A7 days
- B6 months
- C28 daysAnswer
- DThere is no need to tell them
The same period applies to a change of contact details, to anyone in management being convicted of an environmental offence, and to the firm changing what it actually does. Some changes need a fresh registration rather than an update.
Sourcehttps://www.gov.uk/waste-carrier-or-broker-registration
- 24. Working environmentcscs-19
You see something on site that could hurt you or the people around you. What does the law expect?
- AThat you report itAnswer
- BThat you fix it yourself first
- CThat you write it in your own diary
- DThat you tell the client directly
Workers are closest to the job and often see a danger first. Reporting it is a duty, not a favour to the boss. The report is also how the site learns, because the same trap is probably somewhere else too.
- 25. Working environmentcscs-2
An architect is coming to look at the site for one hour, with an escort. What does the site have to give them?
- ANothing, because they will not do any work
- BAn induction that suits a short escorted visitAnswer
- CThe same full induction as a new worker
- DOnly a hard hat and boots at the gate
Visitors get an induction too, but it is scaled to the visit. An escorted visitor needs to know the main hazards and the controls, not the whole site plan. Someone walking round on their own needs much more.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/site-rules-induction.htm
- 26. Working environmentcscs-20
A worker holds an industry card for the trade. Does that on its own prove they can do the job safely?
- AYes, a card settles the question
- BYes, if the card is still in date
- CNo, a card alone is not enough evidenceAnswer
- DNo, cards have no value at all
A card is one piece of evidence among several, not the whole answer. What counts is skills, knowledge, training and experience for the actual task. Nationally recognised qualifications carry more weight, and a worker still building up experience needs supervision.
- 27. Working environmentcscs-206
Under the duty of care for waste, who may a load be handed over to?
- AAnyone with a van and a phone number
- BWhoever offers the lowest price
- CAnyone, once it has left the site
- DOnly an authorised personAnswer
A written description of the load goes across with it, so the next pair of hands can stay within the law too. The duty runs on everyone who produces, carries, keeps, treats or disposes of it, and on brokers and dealers.
Sourcehttps://www.legislation.gov.uk/ukpga/1990/43/section/34
- 28. Working environmentcscs-207
What does the duty of care say about waste escaping from a skip or a lorry?
- AIt is only a problem on the public road
- BIt is the council's responsibility
- CIt must be preventedAnswer
- DIt only matters for hazardous loads
Sheeting a load, keeping lids down and stopping windblown rubbish are all part of the same duty. It runs while the material is in your hands, and it also asks you to stop the next person breaking the law with it.
Sourcehttps://www.legislation.gov.uk/ukpga/1990/43/section/34
- 29. Working environmentcscs-21
The site is changing the way a job is done and it affects your health and safety. What is your employer required to do?
- AConsult you about itAnswer
- BPut a notice on the canteen wall
- CTell you only if you ask
- DGet your written agreement first
Consultation means being asked before the decision hardens, not told afterwards. Workers spot problems that the plan misses. If a change lands on you with no discussion, that is a gap worth naming.
- 30. Working environmentcscs-22
A site in a busy town needs a perimeter. What is normally used?
- AWarning tape on posts
- BA two metre high mesh fence or hoardingAnswer
- CA single rope at waist height
- DCones spaced along the boundary
In a built up area the usual answer is a two metre small mesh fence or a hoarding, because it keeps children out as well as adults. The fence has to be planned, put up and then kept in repair. A gap in it is the same as no fence.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/publicprotection.htm
- 31. Working environmentcscs-23
You are locking up at the end of the day. What should happen to the ladders?
- ALay them flat next to the scaffold
- BChain them to the scaffold standard
- CTake them off excavations and scaffoldsAnswer
- DLeave them for the early start crew
A ladder left in place is an invitation, and children are drawn to sites. Removing it takes a minute and closes off the climb. The same thinking covers covering pits, immobilising plant and locking away chemicals.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/publicprotection.htm
- 32. Working environmentcscs-24
Work is going on above a public pavement. What is the duty about falling objects?
- AWarn people with a sign at the corner
- BStop work whenever a person walks past
- CNothing can be done about wind
- DNothing may fall outside the boundaryAnswer
The public did not choose to be near the job, so the boundary has to hold. Toe boards, brick guards and netting on the scaffold do most of the work, with fans or a covered walkway where needed. A sign does not catch a dropped hammer.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/publicprotection.htm
- 33. Working environmentcscs-247
Whose safety does an employer's risk assessment have to cover?
- AEmployees and nobody else
- BOnly visitors to the site
- CEmployees and other people affectedAnswer
- DOnly people paid by the hour
The assessment is what identifies the measures the law then requires. It has to be looked at again if there is reason to think it no longer holds, or if something significant has changed, and altered where the review says so.
Sourcehttps://www.legislation.gov.uk/uksi/1999/3242/regulation/3
- 34. Working environmentcscs-248
Before work starts, what should a contractor do about the health hazards it creates?
- AWait until a worker complains
- BLeave it to the equipment supplier
- CAssume the usual controls will do
- DIdentify the hazards linked to the tasksAnswer
Then weigh how likely harm is and how serious it could be. The common ones in this trade are asbestos, dust, lifting and carrying, noise, vibration, cement and lead. Workers are brought into the process, not just told about it.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/managing-essentials/assess-the-risks.htm
- 35. Working environmentcscs-25
Under the Health and Safety at Work etc. Act 1974, what duty does an employee have while at work?
- ANone, the duty is all on the employer
- BTo take reasonable care for self and othersAnswer
- CTo write a risk assessment for each task
- DTo report every fault to the inspector
The Act puts a duty on you personally, and it covers other people affected by what you do or fail to do. You also have to co-operate with your employer so their duties can be met. Safety is shared, not handed over.
Sourcehttps://www.legislation.gov.uk/ukpga/1974/37/section/7
- 36. Working environmentcscs-285
In what order does the law want business waste dealt with?
- ARecover, recycle, reuse, then prevent
- BPrevent, reuse, recycle, then recoverAnswer
- CRecycle, recover, prevent, then reuse
- DReuse, prevent, recover, then recycle
The cheapest and safest waste is the load that never arises, so the order runs prevent, reuse, recycle, then recover, and each step down is reached only when the one above it will not work.
- 37. Working environmentcscs-286
Rubble and offcuts leave a building site. What kind of waste is that in law?
- AHousehold waste, once it is bagged
- BInert waste needing no paperwork
- CBusiness waste, like any trade wasteAnswer
- DWaste the council must collect free
Waste is classed by where it comes from, not by what it looks like. Anything arising from a commercial activity is business waste, like any trade waste, and construction and demolition are named as examples.
- 38. Working environmentcscs-287
Portable chemical toilets are being used on a site. How many are needed?
- AOne for every three people
- BOne for every seven peopleAnswer
- COne for every fifteen people
- DOne for every twenty people
The figure is set against a normal working week, so one for every seven people on a forty hour week is what the guidance gives.
- 39. Working environmentcscs-288
Section 33 of the Environmental Protection Act 1990 bars tipping controlled waste on land unless what is true?
- AThe landowner has given written consent
- BThe load weighs under one tonne in all
- CA permit authorising the deposit is in forceAnswer
- DThe waste was produced on that same land
Tipping is controlled by licence rather than by ownership, so it is lawful only where a permit authorising the deposit is in force and the tipping follows what that permit says.
Sourcehttps://www.legislation.gov.uk/ukpga/1990/43/section/33
- 40. Working environmentcscs-289
A householder composts garden waste in their own back garden. How does section 33 treat that?
- AIt is an offence without a permit
- BIt falls outside the deposit offencesAnswer
- CIt needs a transfer note each time
- DIt has to be registered with the council
The section is aimed at waste moving through trade, so household waste kept or disposed of within the grounds of the home falls outside the deposit offences.
Sourcehttps://www.legislation.gov.uk/ukpga/1990/43/section/33
- 41. Working environmentcscs-290
Who does the waste duty of care bind?
- AOnly the firm that finally tips the load
- BOnly the registered carrier moving it
- CAnyone who produces, carries or keeps itAnswer
- DOnly the company that owns the site
The duty runs along the whole chain rather than resting on one link, so it reaches anyone who produces, carries or keeps it, dealers and brokers included even where they only handle paperwork.
Sourcehttps://www.legislation.gov.uk/ukpga/1990/43/section/34
- 42. Working environmentcscs-291
What does regulation 27 of CDM 2015 require of the way a site is laid out?
- AThat plant is parked in one marked area
- BThat deliveries arrive outside work hours
- CThat every gate is manned during the day
- DThat pedestrians and vehicles move safelyAnswer
Most site transport deaths happen where the two flows meet, so the regulation asks that the place be organised so that pedestrians and vehicles move safely, as far as is reasonably practicable.
Sourcehttps://www.legislation.gov.uk/uksi/2015/51/regulation/27
- 43. Working environmentcscs-292
Besides being suitable, what else does CDM 2015 demand of traffic routes?
- AEnough of them, well placed and big enoughAnswer
- BThat they are surfaced with tarmac
- CThat they are lit by mains floodlights
- DThat they are marked out in yellow paint
One narrow road serving a whole job is what forces men and machines together, so the law wants enough of them, well placed and big enough for the traffic they carry.
Sourcehttps://www.legislation.gov.uk/uksi/2015/51/regulation/27
- 44. Working environmentcscs-293
What does Schedule 2 of CDM 2015 say about toilets for men and women?
- AOne block is enough on any small job
- BSeparate rooms, unless each is lockableAnswer
- CSeparate blocks are needed in every case
- DSeparate blocks only above fifty workers
The schedule asks for separate rooms, unless each is lockable from the inside, which is why a single cubicle with a working bolt satisfies it and an open row of pans does not.
Sourcehttps://www.legislation.gov.uk/uksi/2015/51/schedule/2
- 45. Working environmentcscs-294
Where does Schedule 2 of CDM 2015 put the washing facilities?
- ABeside the site entrance for everyone
- BRight next to every toilet on the siteAnswer
- CIn the canteen, where the water already is
- DWherever the site office happens to be
Hands get contaminated where the toilets are, so washing has to be right next to every toilet on the site, whether or not there are sinks elsewhere as well.
Sourcehttps://www.legislation.gov.uk/uksi/2015/51/schedule/2
- 46. Working environmentcscs-295
A job involves cement, lead and old drains. What may that add to the welfare on site?
- AShowers, on top of the usual facilitiesAnswer
- BA first aid room next to the canteen
- CA second canteen for dirty clothing
- DA drying room for wet outer clothing
Some substances stay on the skin long after the shift ends, so the guidance points to showers, on top of the usual facilities, wherever cement, lead or micro-organisms are in the work.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/index.htm
- 47. Working environmentcscs-296
The site rest area is being used to stack bags of plaster. What does the guidance say?
- AIt is allowed if the bags are stacked low
- BIt is allowed while the weather is bad
- CPlant, equipment and materials stay outAnswer
- DIt is allowed if a gangway is left clear
A rest area works only if people can actually use it, so the rule is that plant, equipment and materials stay out and the space is kept clean and tidy.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/changing-rooms-and-lockers.htm
- 48. Working environmentcscs-297
When does a load have to be marked with its weight?
- AWhenever it comes off a lorry
- BWhenever it weighs over 20kg
- CWhere there is a risk of injuryAnswer
- DWhenever it leaves the store
Marking is aimed at surprises rather than at paperwork, so it is called for where there is a risk of injury and doing it is reasonably practicable.
- 49. Working environmentcscs-298
Does a RIDDOR report reach the firm's insurance company?
- AYes, HSE copies every report to insurers
- BYes, but only for reportable diseases
- CNo, the firm has to tell them separatelyAnswer
- DNo, insurers hear it from the injured worker
The two systems are unconnected, so the firm has to tell them separately. Nothing is passed on, and a late claim can cost money that need never have been spent.
- 50. Working environmentcscs-299
A firm has three employees. Do the first aid regulations reach it?
- ANo, they start at five employees
- BYes, they apply to all workplacesAnswer
- CNo, they start at ten employees
- DYes, but only on construction sites
There is no lower threshold at all: they apply to all workplaces, including those with fewer than five employees, and to the self-employed into the bargain.
- 51. Working environmentcscs-3
Half the gang on your site read very little English. What should be done about the site rules?
- ANothing, English is the site language
- BLet the foreman explain them by hand signals
- CConsider having the rules translatedAnswer
- DAsk those workers to sign a waiver
Rules only work if the people bound by them can read them. Where workers do not speak English, translations should be thought about when the rules are written. A rule nobody understands protects nobody.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/site-rules-induction.htm
- 52. Working environmentcscs-300
Do the first aid regulations make an employer provide for members of the public?
- AYes, on any site open to the public
- BYes, wherever visitors sign in at a gate
- CNo, and doing so would breach the rules
- DNo, though including them is advisedAnswer
The legal duty covers employees, so the honest answer is no, though including them is advised: HSE recommends counting outsiders into the needs assessment and providing for them.
- 53. Working environmentcscs-301
What does HSE advise about keeping painkillers in the site first aid box?
- AKeep a week's supply for the gang
- BKeep them, but under lock and key
- CKeep only what the label allows
- DDo not keep tablets or medicinesAnswer
A first aider cannot know what somebody is already taking, so the advice is do not keep tablets or medicines in the box at all.
- 54. Working environmentcscs-302
What is strongly recommended between one first aid qualification and the next?
- AA written test set by the employer
- BA refresher course every yearAnswer
- CA medical check every other year
- DA second certificate from a rival body
Skills that are never used fade quickly and the gap between courses is long, so a refresher course every year is urged to keep the basics usable when they are suddenly needed.
- 55. Working environmentcscs-303
A worker carries an auto-injector for a serious allergy. What does HSE suggest?
- ATelling the employer about itAnswer
- BKeeping it entirely private
- CLeaving it in the site office
- DHanding it to the first aider
An employer cannot plan for what nobody has mentioned, so telling the employer about it lets the first aiders be briefed and trained for that case.
- 56. Working environmentcscs-304
What must every employee be given about the first aid arrangements?
- AThe details of those arrangementsAnswer
- BA copy of the needs assessment
- CA place on a first aid course
- DThe phone number of the insurer
Provision that nobody knows about helps nobody, which is why the law wants the details of those arrangements to reach all employees and not only the supervisors.
Sourcehttps://www.hse.gov.uk/firstaid/what-employers-need-to-do.htm
- 57. Working environmentcscs-305
What does the law demand of the reports of thorough examination of lifting equipment?
- AThat they are kept in the crane cab
- BThat they are renewed every month
- CThat they are sent to the insurer
- DThat they are secure and availableAnswer
A report that cannot be produced proves nothing, so the requirement is that they are secure and available to enforcing authorities, and able to be reproduced in writing.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/admin.htm
- 58. Working environmentcscs-306
Which of these has to be inspected at set times with a report prepared and kept?
- AExcavations, scaffolds and laddersAnswer
- BSite fencing and gates on the road
- CCanteen equipment and rest areas
- DDelivery lorries entering the site
The list covers what fails without warning and kills when it does: excavations, scaffolds and ladders, along with fall arrest systems, all carry timed inspections and retained reports.
Sourcehttps://www.hse.gov.uk/construction/safetytopics/admin.htm
- 59. Working environmentcscs-307
Under the construction health risk guidance, what is the client's part?
- ADoing the health surveillance itself
- BPicking the respirators for the job
- CMaking sure arrangements are in placeAnswer
- DTraining the workers on the hazards
A client controls the money and the timetable rather than the work itself, so the duty is making sure arrangements are in place for managing health risks during the build.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/managing-essentials/who-does-what.htm
- 60. Working environmentcscs-308
What does the same guidance ask of the workers themselves?
- ATo sign a waiver about health risks
- BTo arrange their own health checks
- CTo keep quiet about minor symptoms
- DTo take care and co-operate on healthAnswer
A control works only if the person wearing it agrees to it, so the worker's part is to take care and co-operate on health with everyone else on the job.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/managing-essentials/who-does-what.htm
- 61. Working environmentcscs-309
Is there a legal duty to have portable electrical equipment tested every year?
- AYes, on any construction site
- BNo, the law sets no intervalAnswer
- CYes, for anything over 110 volts
- DYes, for any hired equipment
The duty is to keep equipment in a safe condition, not to test on a calendar, so no, the law sets no interval: it depends on the kit and where it is used.
Sourcehttps://www.hse.gov.uk/electricity/faq-portable-appliance-testing.htm
- 62. Working environmentcscs-385
Hazardous waste is taken off a site. What paperwork does the law require?
- AA consignment note for the removalAnswer
- BA copy of the site risk assessment
- CA letter from the local council
- DAn entry in the site accident book
Hazardous loads are tracked from gate to gate, so a consignment note for the removal is completed whenever the waste leaves the premises.
Sourcehttps://www.legislation.gov.uk/uksi/2005/894/regulation/35
- 63. Working environmentcscs-386
More than one carrier will move a load of hazardous waste. What else may be needed?
- AA second note for every carrier
- BA schedule of carriers with the noteAnswer
- CA police escort for the convoy
- DA separate permit for each vehicle
One note cannot hold an open-ended chain of hands, so a schedule of carriers with the note is completed where that regulation applies.
Sourcehttps://www.legislation.gov.uk/uksi/2005/894/regulation/35
- 64. Working environmentcscs-387
What must an employer weigh before handing a task to a particular worker?
- AHow long the worker has been employed
- BWhether the worker is on a day rate
- CThe worker's capabilities on health and safetyAnswer
- DWhich trade union the worker belongs to
The same job is not equally safe in every pair of hands, so the law asks for the worker's capabilities on health and safety to be taken into account first.
Sourcehttps://www.legislation.gov.uk/uksi/1999/3242/regulation/13
- 65. Working environmentcscs-388
Training was given when a worker joined three years ago. What does the law expect since then?
- ANothing further until they change job
- BA written test once every two years
- CA refund of the cost from the worker
- DRepeating it periodically where neededAnswer
Skills and rules both drift across years, so the requirement is repeating it periodically where needed, and again whenever the risks change.
Sourcehttps://www.legislation.gov.uk/uksi/1999/3242/regulation/13
- 66. Working environmentcscs-389
Someone unhooks a fire extinguisher to prop a door open. Which duty does that break?
- ANot to misuse things provided for safetyAnswer
- BNot to work without a site induction
- CNot to leave the site during a shift
- DNot to enter a building alone at night
The Act binds every person, not just employers: not to misuse things provided for safety, health or welfare, whether deliberately or recklessly.
Sourcehttps://www.legislation.gov.uk/ukpga/1974/37/section/8
- 67. Working environmentcscs-390
Besides taking reasonable care, what else does the 1974 Act ask of an employee?
- ATo pay for their own protective kit
- BTo co-operate with the employerAnswer
- CTo report to the enforcing authority
- DTo keep their own accident record
An employer cannot meet a duty that the workforce quietly works around, so the second limb is to co-operate with the employer as far as is necessary.
Sourcehttps://www.legislation.gov.uk/ukpga/1974/37/section/7
- 68. Working environmentcscs-4
Who has to make sure there are welfare facilities for the people working on a site?
- AEach worker brings their own
- BThe contractor, and the client checks it happensAnswer
- CThe local council provides them
- DOnly the client, and only on big jobs
The duty sits with the contractor, and the client has to make sure the arrangements exist before work starts. It applies to all construction work, big or small. This is why welfare is planned early and not squeezed in later.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/index.htm
- 69. Working environmentcscs-421
A round sign carries a black pictogram on white, with a red border and a red diagonal line through it. What is it telling you?
- ASomething is forbidden hereAnswer
- BSomething must be worn here
- CThere is a hazard ahead, take care
- DThis is the way to the fire exit
Round, white, red border and a diagonal bar is the prohibition sign, and the red has to cover at least 35 per cent of it. No smoking, no pedestrian access and no drinking water all come in that shape. Learn the shape and the colour together and you can read a sign across the site before you can make out the picture on it.
Sourcehttps://www.legislation.gov.uk/uksi/1996/341/schedule/1/made
- 70. Working environmentcscs-422
What do triangular signs with a black pictogram on yellow mean?
- AWarning of a hazardAnswer
- BAn action you must take
- CAn action that is forbidden
- DWhere the first-aid kit is kept
The triangle is always a warning: electricity, overhead load, a drop, a corrosive substance. The yellow has to take up at least half the sign so it reads at a distance. A warning sign tells you a hazard is there, it does not tell you what to do about it, and that is what the method statement is for.
Sourcehttps://www.legislation.gov.uk/uksi/1996/341/schedule/1/made
- 71. Working environmentcscs-423
A round blue sign with a white pictogram is fixed at the entrance to an area. What does it require?
- AYou must do what it shows, such as wear eye protectionAnswer
- BYou must not do what it shows
- CIt marks a first-aid point
- DIt marks where fire equipment is kept
Blue and round is the mandatory sign: safety helmet must be worn, ear protection must be worn, safety harness must be worn. The blue has to take up at least half the sign. Blue is the only colour that orders you to do something, which is worth remembering because blue and red are easy to mix up at a glance.
Sourcehttps://www.legislation.gov.uk/uksi/1996/341/schedule/1/made
- 72. Working environmentcscs-424
Which colour marks emergency escape routes and first-aid facilities?
- AGreen, on a rectangular or square signAnswer
- BRed, on a round sign
- CYellow, on a triangular sign
- DBlue, on a rectangular sign
Green means safety: emergency exit, first-aid post, safety shower, eyewash. The shape is rectangular or square rather than round or triangular. Fire-fighting signs share that same shape but are red, so on a smoke-filled stair the colour is what you go by, not the outline.
Sourcehttps://www.legislation.gov.uk/uksi/1996/341/schedule/1/made
- 73. Working environmentcscs-425
A hazard on site could be designed out or fenced off, but a supervisor decides to put up a sign instead. Is that the right call?
- ANo, a sign is for risk that cannot be controlled any other wayAnswer
- BYes, a sign is always an acceptable control on its own
- CYes, provided the sign is large enough to be read
- DNo, but only if the hazard could kill someone
Signs sit at the bottom of the pile, not the top. They are required where a significant risk remains after everything else has been done, and they are no substitute for a safe system of work or an engineering control. Too many signs make things worse, because people stop reading any of them.
- 74. Working environmentcscs-426
A warning sign was put up for an excavation that has now been backfilled. What should happen to the sign?
- ATake it down, because the situation it refers to has goneAnswer
- BLeave it up until the whole job finishes
- CLeave it up but turn it to face the fence
- DCover it over and leave it in place for the next job
A sign has to come down once the thing it warns about no longer exists. Leaving old signs up is not a harmless habit: it teaches everyone on site that signs do not mean anything, and the next one they ignore will be a live one. The same logic applies to warning cones left out after ice has melted.
Sourcehttps://www.legislation.gov.uk/uksi/1996/341/schedule/1/made
- 75. Working environmentcscs-427
Frost is forecast overnight for a site with an open car park and pedestrian walkways. When is the best time to grit?
- AEarly evening, before the frost settlesAnswer
- BAt midday, when the surface is at its warmest of the day
- CDuring heavy rain, so that the salt spreads itself further
- DAfter the first person has slipped and reported the fall
Salt is not instant. It needs time to dissolve into the moisture already on the surface, so it goes down before the frost forms or before the first shift walks in. Gritting in heavy rain wastes it, because the salt washes away and leaves you worse off if the rain turns to snow.
- 76. Working environmentcscs-428
Warning cones were put out on an icy path. The ice has since melted. What should be done with them?
- ARemove them, or people learn to ignore the conesAnswer
- BLeave them out for the rest of the winter
- CMove them to the nearest doorway
- DLeave them and add a written notice explaining why
Cones left standing over a dry, safe path train everyone walking past to step around them without thinking. The next set of cones, put out for something real, gets the same treatment. Clearing them once the hazard has gone is part of the control, not tidying up afterwards.
- 77. Working environmentcscs-429
Where should gritting be concentrated on a site in freezing weather?
- ABuilding entrances, car parks, walkways, slopes and shaded areasAnswer
- BOnly the main road outside the site gate
- COnly inside the welfare cabins
- DWherever the wind has blown the snow into drifts
The list is the places people actually walk and where ice forms first: doorways, parking, footpaths, shortcuts, sloping ground and anywhere permanently in shade or wet. Areas in shade stay frozen long after open ground has thawed. If you cannot cover everything, say publicly which paths you are treating.
- 78. Working environmentcscs-430
A floor gets contaminated with water or mud over and over during the working day. What does that mean for the surface itself?
- AIt has to be one people can still walk on without slippingAnswer
- BIt only matters if the contamination is oil rather than water
- CNothing, as long as a wet floor sign is put out each time
- DNothing, provided the floor is mopped at the end of each shift
Where contamination keeps coming back, the answer is a floor that stays walkable when wet, not a sign put out after the event. Rougher safety flooring does exactly that, and it takes a little more effort to clean, which is the trade you accept. Signs and mopping deal with the one-off spill, not the recurring one.
- 79. Working environmentcscs-431
What must an employer protect a young worker from, over and above the risks facing everyone else?
- ARisks arising from their lack of experience and awarenessAnswer
- BRisks arising only from lifting heavy loads
- CRisks arising only from working outside in bad weather
- DNothing extra, since the same rules cover everyone
The law names three things about young workers: lack of experience, absence of awareness of risks that exist or may arise, and the fact that they have not yet fully matured. The duty is specific and additional. On site it shows up as closer supervision and jobs chosen to match, not as a lecture on the first morning.
Sourcehttps://www.legislation.gov.uk/uksi/1999/3242/regulation/19
- 80. Working environmentcscs-432
Which of these must a young person not be given as work?
- AWork beyond their physical or psychological capacityAnswer
- BAny work at all that involves using hand tools
- CAny work that takes place outdoors
- DAny work that continues after four in the afternoon
The bar is capacity, not the job title. The same regulation also rules out harmful exposure to toxic or cancer-causing agents, to radiation, and work where the risk of an accident cannot reasonably be spotted or avoided by someone with their level of experience. Ordinary tool work outdoors is not on the list.
Sourcehttps://www.legislation.gov.uk/uksi/1999/3242/regulation/19
- 81. Working environmentcscs-433
Besides toxic substances and radiation, which risk to health is named as off limits for young workers?
- AExtreme cold or heat, noise, or vibrationAnswer
- BBright artificial lighting
- CStanding for more than two hours at a time
- DWorking within sight of moving traffic
Those three are named in the regulation itself. It is worth knowing because they are everyday site conditions rather than exotic ones: a breaker, a cutting saw and an unheated slab in January all land squarely on that list. Whether the work is allowed then turns on the exception for training under supervision.
Sourcehttps://www.legislation.gov.uk/uksi/1999/3242/regulation/19
- 82. Working environmentcscs-434
An apprentice over school leaving age needs to learn a task that is normally off limits for young workers. What makes that lawful?
- ATraining need, proper supervision, and risk cut to the lowest levelAnswer
- BThe apprentice signs a form agreeing to take on the work
- CA parent gives written permission for the work to go ahead
- DThe task takes less than one hour in any single working day
All three conditions have to hold together, not one of them: the work is needed for training, the young person is supervised by someone competent, and the risk is reduced to the lowest level that is reasonably practicable. The exception is narrow on purpose, so that apprentices can learn a trade without it becoming a way round the ban. Consent, from the young person or a parent, is not one of the conditions and does not make unsafe work safe.
Sourcehttps://www.legislation.gov.uk/uksi/1999/3242/regulation/19
- 83. Working environmentcscs-435
A young worker is told to do a job where an accident could happen that an inexperienced person would not see coming. What is the position?
- AThat work is ruled out for them unless the training exception appliesAnswer
- BIt is fine as long as somebody else is working nearby
- CIt is fine as long as they have been given a hard hat
- DIt is fine as long as the job is finished before dark
The regulation names this exact case: risk of accidents that it may reasonably be assumed cannot be recognised or avoided by young persons because of insufficient attention to safety, or lack of experience or training. Somebody working nearby is not the same thing as being supervised, and a hard hat is not a control for a hazard you cannot see coming.
Sourcehttps://www.legislation.gov.uk/uksi/1999/3242/regulation/19
- 84. Working environmentcscs-5
Which facilities must everyone working on a construction site be able to reach?
- AToilets and washing only
- BToilets, washing, changing, eating and restAnswer
- CA canteen with hot meals every day
- DWhatever the site manager decides to buy
The list is fixed, not a matter of taste. Access matters as much as the facility itself, so on a big site the walk to the nearest one has to be kept short. Extra things like showers may be needed if the work is dirty or uses cement or lead.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/index.htm
- 85. Working environmentcscs-6
Where should washing facilities be put on site?
- AAnywhere with a water supply
- BNext to the toilets and changing roomsAnswer
- CInside the rest and eating area
- DAt the site entrance, near the gate
People wash when washing is easy. Putting the sinks next to the toilets and the changing area means hands get cleaned at the moment they are dirty. It also keeps the dirty end of the site away from where food is eaten.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/toilets-and-washing.htm
- 86. Working environmentcscs-7
A site has only cold water at the sinks. Is that enough?
- AYes, if there is soap as well
- BYes, if hand gel is provided too
- CNo, hot or warm running water is neededAnswer
- DYes, in summer but not in winter
Cold water does not shift cement, oil or dust from skin. Washing facilities have to give hot and cold or warm running water, something to clean with and something to dry with. Basins also need to be big enough to wash your forearms, not just fingertips.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/toilets-and-washing.htm
- 87. Working environmentcscs-8
The only sink on site is in the corner of the canteen. Why is that a problem?
- AWashing should not usually happen where people eatAnswer
- BThe queue slows down the lunch break
- CSinks are always noisy at meal times
- DCanteens are not allowed to have taps
Whatever is on your hands ends up on the tables and in the food. Keeping washing away from eating areas is the point, and it matters most when the work involves cement, lead or dirty water. The sink has to go somewhere else.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/toilets-and-washing.htm
- 88. Working environmentcscs-84
A worker is hurt in an accident and cannot do their normal job for nine days. What does the law require?
- ANothing, unless they go to hospital
- BA report, because it is over seven daysAnswer
- CA report only if the employer is at fault
- DA note in the site diary only
Being unable to do the normal work for more than seven consecutive days after the day of the accident makes it reportable. The count leaves out the day it happened. Blame does not come into whether the report is needed.
- 89. Working environmentcscs-85
Who makes the report to the enforcing authority when there is a reportable accident?
- AThe injured person themselves
- BThe responsible person, such as the employerAnswer
- CAny workmate who saw it happen
- DThe first aider who treated it
The duty sits with the employer or whoever is in charge of the premises, not with the person who was hurt. You can still raise a concern with the regulator separately if you think something is wrong. Both routes exist for different reasons.
- 90. Working environmentcscs-86
A worker develops a bad back from years of repeated lifting. Is that an accident for reporting purposes?
- AYes, any work injury is an accident
- BYes, if a doctor writes it down
- CNo, gradual harm is not an accidentAnswer
- DNo, unless it happened on site
An accident has to be a separate identifiable event, like a falling object striking someone. Harm that builds up over years is not counted that way, though some diseases are reportable in their own right. Feeling a sharp pain on its own is not an accident either.
- 91. Working environmentcscs-87
What must an employer keep after a reportable injury or dangerous occurrence?
- ANothing, the online form is enough
- BA record of itAnswer
- CA copy of the worker's contract
- DA statement from every witness
The record has to be kept even after the report is sent. If no copy of the form was saved, it must cover the date and method of reporting, the time and place, who was involved and what happened. Records are what show a pattern before the next injury.
- 92. Working environmentcscs-88
How long does a first aid at work certificate last?
- AOne year
- BThree yearsAnswer
- CFive years
- DIt does not expire
After that the holder has to requalify, and until they do they are not counted as a workplace first aider. Annual refresher training in between is strongly advised because the skills fade. Check the dates before you rely on someone.
- 93. Working environmentcscs-89
What training does an appointed person for first aid have to hold?
- ANone is requiredAnswer
- BA full first aid at work certificate
- CAn emergency first aid certificate
- DA nursing qualification
The appointed person looks after the kit and calls the emergency services, which needs no formal course. That is the minimum where the needs assessment says a trained first aider is not required. Somewhere with machinery or hazardous materials will normally need more.
Sourcehttps://www.hse.gov.uk/firstaid/what-employers-need-to-do.htm
- 94. Working environmentcscs-9
What should a site rest area have for the people using it?
- AStanding space and a kettle
- BEnough tables and seats with backsAnswer
- CA television and free newspapers
- DOnly somewhere out of the rain
A rest area is meant for resting, so there must be enough tables and proper seats for everyone likely to be in there at once. There also has to be a way to heat water and prepare food. Storing materials or plant in there stops it being a rest area.
Sourcehttps://www.hse.gov.uk/construction/healthrisks/welfare/changing-rooms-and-lockers.htm
- 95. Working environmentcscs-90
Someone uses the last two dressings from the site first aid kit. What should happen?
- AWait for the monthly stock check
- BRestock it soon after useAnswer
- CMove the kit to the site office
- DNote it and use another kit
A kit is only useful if it is full when the next person needs it. The contents get checked often and topped up quickly after any use. It also has to stay somewhere people can reach it fast.
Sourcehttps://www.hse.gov.uk/firstaid/what-employers-need-to-do.htm